The A465 Belmont Road shuts for 10 nights from 14 September, Gaol Street for two days from 24 September. Every road in the county's September order, dated.

Herefordshire Council has published the statutory notices for its September road programme, and the biggest single item in it is in the city. The A465 Belmont Road is down for closure for 10 nights from 14 September. Two weeks later, Gaol Street is scheduled to shut for two days from 24 September.

Both sit inside one order covering 22 roads, which comes into force on 31 August. This page lists every road in it, what is already closed today, where to park and what it costs, and where the bypass has got to.

Last checked 22 August 2026.

Closed now, or in the next fortnight

These orders have been made, which means the council has taken the decision rather than announced an intention.

Herefordshire road and footpath closures in force or starting within a fortnight, from orders made and advertised by Herefordshire Council in August 2026
WhereFromForWhy
Public footpath ZK9, Ross-on-Wye20 AugustUp to 6 monthsDamaged footbridge
B4214 Old Road, Bromyard, by Firs Orchard24 August5 daysBurst main
C1273 Brampton Road, Greytree, Ross-on-Wye24 August1 day, 9.30am to 3.30pmOverhead cabling
Footpaths WH16 Wellington Heath and part of LR17 Ledbury Rural24 AugustUp to 6 monthsDamaged footbridge
B4348 outside Peterchurch primary school27 August2 nightsNew pedestrian crossing
Friars Street, Hereford, at Cross Street29 August1 nightAnti-skid surfacing and lining

Three of those matter more than the rest.

  • Bromyard. Old Road is shut next to the Firs Orchard junction for five days from Monday. The signed diversion runs via the A44, Sherford Street, Broad Street and High Street.
  • Ross-on-Wye. The footpath closure at ZK9 has no end date beyond “until the works are done”, with a six-month backstop. The alternative route is via Trenchard Street, Horns Road and the rest of ZK9.
  • Ledbury and Wellington Heath. The footbridge closure on WH16 and LR17 has no alternative route at all. The council’s own notice says so. If you walk that link, there is nothing to divert onto.

The Courtyard’s car park on Edgar Street is also still closed. The theatre says on its own site that there is no on-site parking throughout August and that the car park reopens on Friday 4 September, while its pop-up venue The Amp occupies the site.

The September order: 22 roads, from 31 August

On 13 August the council gave notice that it intends to make the Resurfacing and Patching Scheme Sept 26 order. It comes into force on 31 August 2026 and the whole programme is expected to take about a month.

Read the dates below as proposed. This is a notice of intention, not a decision already taken, and the council states that definitive dates and times will be given by advance warning signs on site.

Schedule 1 of the Resurfacing and Patching Scheme Sept 26 Temporary Road Closure Order 2026, as advertised by Herefordshire Council on 13 August 2026
RoadTown or parishProposed startDuration
Golden PostHereford1 September1 day
White Rocks Access RoadGarway Hill1 September4 days
Churchfields Road from Welsh Court RoadYatton1 September2 days
A438 from Portway to Offa's DykeByford1 September1 day
A465 from C1118 to Ridgeway RoadCross Keys2 September3 days
A480 from A44 to Stocks LaneLyonshall3 September7 days
Winsley Road, Village Road to Bromwell FarmHope-under-Dinmore4 September3 days
A417 from C1118 to Felton Court RoadFelton7 September5 days
Trenchard StreetRoss-on-Wye7 September5 nights
Edde Cross StreetRoss-on-Wye7 September5 nights
Bridge StreetKington8 September1 night
Welsh Court Road, Gwynns Hill to Rocks Place RoadYatton10 September5 days
A4111 from Spond Lane to Church RoadEardisley10 September6 days
A465 Belmont RoadHereford14 September10 nights
Bonington DriveHereford14 September5 days
Hillary DriveHereford14 September5 days
B4224 from B4225 to Fording LaneUpton Bishop14 September5 days
U93404 Birley Road, Barley Croft to Honey Lake BrookAulden14 September3 days
B4230 from Hinton Lane to A438Mansel Gamage21 September5 days
Gaol StreetHereford24 September2 days
B4232 Jubilee DriveUpper Colwall24 September3 weeks
B4352 from Merbach to Lawn GateBredwardine28 September5 days

What that means if you drive in Hereford

Belmont Road is the one to plan around. The A465 is the main southwestern approach to the city, and 10 nights is the longest closure of any road in the city in the order. It is night work, so the daytime commute should be unaffected, but anyone driving in or out late will be on a diversion for a fortnight.

Gaol Street is a car park street. Herefordshire Council’s own Gaol Street car park, 130 spaces, sits on it. The order covers the road, not the car park, and the council has not said whether access to the car park is maintained during the two days. If you use it, check the advance signs before 24 September rather than assuming.

Bonington Drive and Hillary Drive are off Kings Acre Road on the western edge of the city, and both are down for five days from the same Monday as Belmont Road.

Water mains work around Leominster, from 7 September

A second order, also advertised on 13 August, covers water mains renewal preparation and comes into force on 7 September. It is expected to take about four weeks and lists 12 closures in the parishes north of Leominster.

The road it hits hardest is Eye Lane (C1048), which appears four times: at Ashton from 10 September for two days, at Moreton Eye from 10 September for seven days, at Eye from 15 September for four days and at Luston from 17 September for seven days.

Also in the order:

  • C1050 Hundred Lane from the A49, at Ashton and at Middleton, both from 7 September for three days
  • Lower Easton, Leysters, from 9 September for two days
  • C1049 Pateshall Lane, Kimbolton, from 14 September for three days and again from 17 September for two days
  • C1052 from Lower Easton to the C1049, Middleton, from 14 September for two days
  • The Hawthorns, Kimbolton, from 21 September for three days
  • Woonton Lane, Middleton, from 24 September for two days

Further ahead: four dates worth diarising

Herefordshire road closures advertised as notices of intention in August 2026 for work later in September
WhereProposed startDurationWhy
Green Lane, Leominster, Radnor View to Cranes Lane1 September6 weeksGas mains renewal
B4216 near Hazle Farm, south of Full Pitcher roundabout, Ledbury14 September3 daysTrenching and cable diversion
C1196 Madley, Parkway Bungalows to Middle Brampton Farm14 September2 weeksDrainage
A44 Mill Street, Leominster, either side of the level crossing19 September1 night, 10.30pm to 9.40amLevel crossing maintenance

Two of those bite harder than their length suggests. Green Lane in Leominster is six weeks, the longest closure anywhere in the county’s current notices, with the diversion running via the A44 and Pierrepont Road. And the A44 Mill Street closure takes out the main road through Leominster for a night, with traffic sent the long way round via the A4112, A438 and A49.

There is also a temporary 40mph limit on the A4111 at Kington, about 500 metres either side of Lower Lilwall, proposed for one day from 14 September.

Parking in Hereford, and the £11.50 difference

Herefordshire Council runs around 4,374 off-street parking spaces across the county and about 1,600 controlled on-street spaces. 2,632 of the off-street spaces are in Hereford, banded into three zones: Zone 1 central, Zone 2 visit, Zone 3 work and stay.

The zones are a polite way of saying the price varies by a factor of three.

Hereford council car park charges, one hour against all day Bar chart of Herefordshire Council car park charges in Hereford, Monday to Saturday, August 2026. Merton Meadow costs £1.10 for one hour and £5.50 for up to 24 hours. The Garrick Multi Storey costs £1.70 for one hour and £8.40 for over four hours. Gaol Street costs £1.90 for one hour and £17 for over eight hours. Maylord Orchards costs £1.90 for one hour and £17 for over eight hours. A full day in Hereford costs £5.50 or £17, depending on the car park Herefordshire Council car park charges, Monday to Saturday, checked 22 August 2026. The first 30 minutes is free everywhere. one hour all day Merton Meadow £1.10 £5.50 for 24 hours Garrick Multi Storey £1.70 £8.40 over four hours Gaol Street £1.90 £17.00 Maylord Orchards £1.90 £17.00 Merton Meadow is about a ten minute walk further from High Town than Maylord Orchards, and £11.50 cheaper for the day. Sunday tariffs are lower everywhere: £6 all day at Gaol Street and Maylord Orchards, £3.30 at Merton Meadow. Source: Herefordshire Council car park pages. Chart by Hereford Today.
Chart by Hereford Today

If you are in town for the day, Merton Meadow (HR4 9HE) is the answer: £1.10 an hour, £4.40 for four hours and £5.50 for up to 24 hours, Monday to Saturday. The Garrick Multi Storey (HR4 9HG) is next at £8.40 for anything over four hours, with 399 spaces, 12 disabled bays, 18 parent and child bays and a 2.2 metre height limit.

Gaol Street (HR1 2HU, 130 spaces) and the underground Maylord Orchards (HR1 2DT, 208 spaces) are the central ones, and they are the ones to avoid for a long stay: £1.90 an hour rising to £17 for over eight hours. Maylord Orchards has a 1.98 metre height limit and closes behind a shutter outside its hours, with a £15 fee to release a vehicle left inside.

Three rules that apply everywhere:

  • The first 30 minutes is free, in every council car park and every on-street pay-and-display bay in the county, under the Pop and Shop scheme introduced on 23 April 2026. You still have to get a ticket from the machine, and you cannot claim it through the JustPark app.
  • Blue Badge holders get three hours free in council pay-and-display car parks, with a valid badge and clock displayed.
  • Season tickets run to £1,373 a year at the Garrick and £858 at Merton Meadow. There is also an off-peak season ticket at £99 a year, valid 5pm to 9am, available across the Hereford car parks.

Since 9 May 2026, private vehicles have had to use the station car park to pick up or drop off at Hereford railway station, because the old kerbside arrangement has gone while the Transport Hub is built.

None of those prices are changing yet, but the framework behind them is. On 31 July 2026 the council’s Cabinet adopted a Herefordshire Parking Strategy running to 2041, shaped by more than 470 consultation responses. It commits the council to protecting disabled bays, tackling obstructive parking around schools and junctions, and treating Hereford, the market towns and rural areas differently. It sets no new tariffs, so read it as the framework for future decisions rather than a price change.

The £37 million road programme, and what is already done

On 23 March 2026 the council set out a £37 million investment in roads, footpaths and public spaces for 2026/27: £23.697 million of Government highways maintenance funding, £6.385 million of highways infrastructure investment, £5 million specifically to resurface roads, £1 million for public rights of way, £945,000 for town and parish council environmental improvements and £600,000 to deal with ash dieback in roadside trees.

That buys 142 road schemes: 32 on A roads, 31 on B roads, 37 on C roads and 41 on unclassified roads. Around 20 miles will be fully resurfaced and a further 64 miles will get surface dressing.

By 22 August the council’s own programme page had marked a long list complete, including the A4110 Wigmore to Adforton, the A4113 from Brampton Bryan to the C1006 at Letton, the B4221 Upton Crews to Hill Top, the A449 approach to the Woodredding bends, the C1114 at Bodenham, the A4137 at St Owens Cross and the B4361 Hereford Road. All seven were still outstanding when we last checked in early August.

The practical point on timing has not changed. The council does not publish start dates on its own scheme pages. Each entry links out to the national one.network map, and those links generally only go live about ten days before work starts, which the council states on the page itself. A live link is therefore a useful signal in its own right: it means the work is close.

The bypass, and what happened this month

On 4 August 2026 the council published the Full Business Case for Phase One of the Hereford Bypass. It is the first time the scheme has been costed and justified in that detail, and the council says one reason for producing it was to show the scheme represents value for money.

The document describes Phase One as a new 3.6km link between the A49 and the A465, serving the Rotherwas Industrial Estate and Hereford Enterprise Zone. Modelling in it suggests journeys between the A465 and the Enterprise Zone could be about six and a half minutes quicker by the design year.

The council also names the residential roads it expects to carry less traffic as a result: Belmont Road, Walnut Tree Avenue and Holme Lacy Road. Belmont Road is the same road losing 10 nights to resurfacing next month.

Construction of Phase One is still scheduled to begin in December 2026, with planning permission secured. Phase Two, which would complete the route and bring a second Wye crossing, has no construction date.

The council’s wider case for the scheme, that up to 14,000 new homes and 150 hectares of employment land cannot be delivered without it, is published on a page that also links to a “Back the Bypass” campaign. Read it as advocacy rather than independent assessment. The December date is the part that will affect your journey.

Walking, cycling and the city centre schemes

In May 2026 the council gave this position on the five main city schemes:

Hereford transport schemes and their stage, as reported by Herefordshire Council in May 2026
SchemeStageExpected finish
Great Western Way cycle route, north HerefordConstruction almost complete2026
Hereford Transport HubAround 65% completeOctober 2026
Holme Lacy Road walking and cycling, south HerefordAround 30% completeWinter or spring 2026/27
Aylestone Hill walking and cyclingDesign complete, construction from June 2027December 2027
Commercial Road, Blueschool Street and NewmarketDesign work summer 2026, construction from June 2027October 2027

The two to watch are the last pair. Aylestone Hill and the Commercial Road, Blueschool Street and Newmarket corridor both carry heavy traffic into the city centre, and both are down for construction starting in June 2027. Neither is a 2026 problem; both are worth knowing about before you commit to a commute.

If you would rather not drive at all, Beryl hire bikes have bays across the city including the railway station, Old Market and the Cathedral, on more than twenty miles of traffic-free path. A pedal bike is £1 to unlock and 5p a minute, an e-bike £1.50 and 12p a minute, and a day pass on a pedal bike is £12.

Common questions

What roads are closed in Hereford right now?

Friars Street at the Cross Street junction closes for one night from 29 August. Further out, Old Road in Bromyard is shut for five days from 24 August and Brampton Road at Greytree for a day. The bigger city closures are next month: A465 Belmont Road for 10 nights from 14 September and Gaol Street for two days from 24 September.

Where is the cheapest place to park in Hereford?

Merton Meadow car park, HR4 9HE, at £5.50 for up to 24 hours Monday to Saturday and £3.30 all day on Sunday. Gaol Street and Maylord Orchards, both more central, charge £17 for the same length of stay.

Is there free parking in Hereford?

The first 30 minutes is free in every Herefordshire Council car park and on-street pay-and-display bay, one session a day, under the Pop and Shop scheme. You must still take a ticket from the machine. Blue Badge holders get three hours free.

When does the Hereford bypass start?

Herefordshire Council says construction of Phase One is scheduled to begin in December 2026. The Full Business Case, published on 4 August 2026, sets it out as a 3.6km link between the A49 and A465 serving Rotherwas. Phase Two has no date.

How do I check Hereford roadworks?

Through the council’s roadworks map, which is the national one.network map. Individual scheme links on the council’s resurfacing pages usually only go live about ten days before work begins. The statutory closure notices, which carry the actual dates, are published in the Public Notice Portal.

Can I be dropped off outside Hereford station?

No. Since 9 May 2026 private vehicles have had to use the station car park for pick-up and drop-off while the new Transport Hub is under construction. The hub was around 65% complete in May, with an October 2026 finish expected.

Sources

Most of the September dates above come from notices of intention, which are proposals rather than decisions already taken. The council says definitive dates will be given by advance warning signs on site. Check before you plan a journey around any of them.